Tags: administrative procedure, architecture engineering, campus projects, classroom laboratory, department of architecture, facilities administration, facilities management services, federal governments, functional categories, interior spaces, laboratory office, landscape services, lease requests, m office, minor alterations, periodic audits, services maintenance, space utilization, subject requests, www facilities,
ADMINISTRATIVE PROCEDURE Effective: February 15, 2001
Subject: Requests for Facilities Management Services (RFMS)
Special Services, Maintenance, Minor Alterations, Lease Requests, Campus
Projects and Capital Projects
Responsible Administrative Unit:
Facilities Management (FM), consisting of the following:
Department of Architecture, Engineering & Construction (AEC)
Department of Building and Landscape Services (B&LS)
Department of Facilities Planning (FP)
Department of Operations and Maintenance (O&M)
Office of Facilities Administration (OFA)
Applicable Form: Request for Facilities Management Services
[Available at www.facilities.umd.edu/RFMS]
______________________________________________________________________________
A. PURPOSE This statement is provided to all units/departments as a guideline to the
policies and proper procedures for requesting the services of FM. These
services include the following: Special Services, Maintenance, Minor
Alterations, Lease Requests, Campus Projects and Capital Projects.
B. POLICY
1. FM has been charged with the responsibility for management of campus facilities.
FM maintains a complete inventory on the assignment and utilization of all
interior spaces. Periodic reports are made to the State and Federal governments
on space utilization as classified by different functional categories (e.g.,
classroom, laboratory, office, etc.) and conditions of facilities. Periodic audits are
conducted to determine the validity of these reports.
1
2. Divisions and colleges are generally expected to accommodate facilities needs
within the space that is assigned to the division/college. Requests for additional
space must follow the procedures for lease requests or capital projects.
3. Departments are not authorized to make the following modifications to existing
buildings (e.g., architectural modifications, heating, ventilation and air
conditioning systems, electrical systems, plumbing systems, etc.) or equipment
(e.g., fume hoods, audio visual, etc.) that impact the building systems without the
prior review and approval of the proposed modification by FM and other
appropriate approval authorities. (Note: Carpet installation/replacement can be
purchased directly through the Department of Procurement and Supply (DPS)
x55831.)
4. Requests for services from FM must be submitted through the review and
approval chain on a Request for Facilities Management Services form. Note:
Maintenance items and/or operations problems of an emergency nature may be
requested over the telephone by calling Work Control (x52222). Requests for
services must be funded by the requesting department or funded by central
university funds approved by the Facilities Council or the Facilities Improvement
Subcommittee.
5. Projects funded by the requesting department in space assigned to them may be
2
approved by FM contingent upon customer and VP review and approval of the
project scope, budget and schedule. No dollar limit is placed on this delegated
authority, but Facilities Council review may be requested at the discretion of the
Director of FP.
6. All requests, which seek partial funding from central university funds for campus
projects, must be accompanied by a detailed budget prepared by FP for which
there is a charge of $500.
7. Due to the limitations of the central university funds, project cost sharing is
encouraged. The general cost sharing guideline for campus projects funding
requests is that the customer provides one half of the amount with the university
contributing one half, if the project is approved. Adjustments to this guideline
may be made in the funding recommendation to accommodate the financial
situations of the requesting department.
8. Any funding required over the approved authorization must be borne by the
responsible school/college/division.
9. The Facilities Council (FC) oversees - at a high level - the use, maintenance,
upgrade, and planning for the university's facilities. The Council decides upon
major space reassignments, allocation of funds for new buildings and major
renovation projects, prioritization of capital construction and renovation projects,
3
and oversees the short-term and longterm facilities planning, including the
campus Facilities Master Plan. The Council approves program statements and
design concept plans for all university facilities. The Facilities Council meets
once a month. All projects that require Facilities Council approval are routed
from FP to the Facilities Council. Facilities Council approval is required for
projects under the following circumstances:
· budgeted to cost more than $100,000 for which the department is
requesting partial funding;
· budgeted to cost more than $100,000 and involve a change in space
utilization, assignment or configuration that crosses divisional lines
i.e., between one Vice President and another, or space assigned to the
university (e.g., classrooms, mechanical rooms, hallways, etc.); and/or
· that involve the lease or purchase of space (e.g., off-campus lease
space, trailers or modular buildings); and
· involving major policy issues.
4
10. The Facilities Advisory Committee (FAC) advises the Facilities Council
regarding projects to be included in the university's facilities budgets. FAC is
informed of site selection issues for new facilities. With input from FM, FAC
reviews and makes priority recommendations to the Facilities Council for annual
facilities project submissions from the colleges/schools/divisions for projects to
be included in the capital budget programs, including the:
· Capital Improvement Program (CIP)
· System Funded Construction Program (SFCP)
· Access Maryland Program (AMP)
· Access UM Program
· Occupational Safety and Health Administration (OSHA) Program
· Various environmental programs (asbestos, chlorofluorocarbons, etc.)
Recommendations for these capital budget programs are developed during the fall
semester.
FAC also reviews and makes priority recommendations for the annual facilities
project submissions from the colleges/schools/divisions for projects to be funded
from central university funds including the:
· Facilities Renewal Program (FRP)
· Facilities Council Program (Central Funds).
Recommendations for use of central university funds are developed during the
spring semester.
All project submissions that request partial funding require a detailed project
5
budget to be provided by FP. All funding requests over $100,000 are to be
reviewed by FAC which makes recommendations to the Facilities Council on
projects to be included in the annual capital budget programs. The Facilities
Council approves all projects to be included in these annual capital budget
programs. Funding approval by the University System of Maryland Board of
Regents (for SFCP) and/or the Maryland State Legislature (for CIP, FRP, AMP
and the environmental programs) is required before proceeding with
implementation. FP provides staff support for FAC and Facilities Council.
11. All projects that require Facilities Improvement Sub-Committee (FIS) approval
are routed from FP to FIS. FIS meets as needed to quickly address project
requests. FIS approval is required for projects under the following circumstances:
· budgeted at $100,000 or less for which the department is requesting
partial funding;
· budgeted at $100,000 or less and involve a change in space utilization,
assignment or configuration that crosses divisional lines i.e., between one
Vice President and another, or space assigned to the university (e.g.,
classrooms, mechanical rooms, hallways, etc.);
· that involve the siting of satellite dishes and antennas.
12. The Teaching Facilities Committee (TFC) advises the Facilities Council and the
Provost on all teaching related facilities issues. An annual call will be made by
TFC to the Deans requesting suggestions for classroom improvement projects.
6
All requests for changes to teaching facilities and facilities actions that may affect
teaching facilities must be reviewed by TFC. A representative of the TFC will be
involved at all stages of the project.
13. The UM Architectural Design Standards Board (ADSB) is the group charged to
develop design guidelines and standards for architecture and the landscape and to
assist in the development of a UM Architectural Review Board. The ADSB also
is charged to assure the aesthetic quality and design coherence for the campus as
well as to review design of new facilities and renovation projects until the
Architectural Review Board is established. The major focus of the ADSB is on
new construction and renovation/renewal projects that will result in a visible
change to the exterior campus environment. The ADSB meets as needed and
reports to the Facilities Council through the Assistant Vice President for Facilities
Management.
14. Major Building Committees are established for capital projects and include
representatives from the occupants of the new or renovated facility as well as
representatives who will address broader land use development and open space
issues for the university.
PROCEDURES
1. Customer completes a Request for Facilities Management Services (RFMS) form and
7
submits it to Work Control. A Financial Record System (FRS) number is required for
processing the form. Note: If a form is not submitted by the requestor, the first point of
contact in FM will provide assistance to the customer to complete a RFMS form and
forward to Work Control.
2. All emergency service items are directed to Work Control via a phone call.
3. All incoming requests are reviewed by a Work Control staff member who assigns a
number, enters the item in the database, then routes the item to either AEC, B&LS, FP or
O&M according to the type of service requested.
4. Specific procedures follow for each of the six services provided by FM.
a. Special Services
Special services include requests for assistance to support special events.
Examples include: extra cleaning services, set up of tables and chairs, providing
electrical power, supplying microphone/speakers/podium and other equipment,
moving units, and assistance with packing for moves.
The cost of providing these services must be paid by the requesting department.
These requests are routed directly to B&LS or O&M by Work Control.
8
b. Maintenance
Maintenance is the recurrent, day to day, periodic or scheduled work
required to preserve or restore a facility to such condition that it can
effectively be used for its designated purpose.
Examples of maintenance work that might be requested by building occupants
include: broken doors, water coming into facility from a leaking pipe, roof or
ground seepage, toilet backup, no heat, no air conditioning or improper
functioning of the heat or air conditioning.
The university funds maintenance of facilities occupied by state-supported units.
Auxiliary units (i.e., Intercollegiate Athletics, Dining Services, Residential
Facilities, Campus Recreation Services, etc.) are responsible to provide funding
for the maintenance of facilities they occupy. B&LS and O&M have separate
agreements with each auxiliary unit and maintenance is performed by B&LS and
O&M as a reimbursable cost.
These services may be called in to Work Control (x52222) if they are of an
emergency nature. There is no charge to state-supported units for these services.
These requests are routed directly to B&LS or O&M by Work Control.
c. Minor Alteration
9
A minor alteration is defined as work in a facility that is beyond
maintaining an existing building component. For this type of work, there
is no space use change and no design services required. This type of work
is intended to move quickly ("fast track") into implementation.
Examples of minor alterations include: making/installing signs (room number
and name plates), bulletin boards, shelves, counters, replacing window air
conditioning units, fans, mail boxes, show cases, electric outlets, switches,
lighting fixtures, carpet or moveable equipment, completing repairs to
departmental furniture, unscheduled room painting, making multiple keys, lock
core changes, lock function changes, installing padlocks or other security
devices/systems, and small modification projects determined by O&M to be able
to be performed by the In-house Construction unit. Work is performed by B&LS
or O&M as a reimbursable cost.
These requests are routed directly to B&LS or O&M by Work Control.
d. Lease Requests
Lease requests are for additional space requirements that can be located in rental
facilities off campus.
A university unit requiring space must first obtain signatures from the respective
10
Dean and Vice President indicating that no space is available in the
college/division to satisfy the requirement.
The RFMS is then forwarded to the Director of FP. In the request, the unit should
identify the source of funding for the monthly lease payments for the term of the
required lease and the associated one-time moving, tenant improvement,
brokerage and related transaction costs if the unit will provide funding. If funds
are being requested from the university, the unit should identify the request on the
RFMS.
If FP determines that there is no on-campus space available, FP will advise the
Vice President for Administrative Affairs who will gather the latest leasing
market information for off-campus space. The off-campus space need will be
forwarded to the Facilities Council for approval. The Council will authorize a
fund source and an estimated funding amount and the designee of the Vice
President for Administrative Affairs will work with the prospective tenant to lease
the most suitable off-campus space at market rates.
The designee of the Vice President for Administrative Affairs will negotiate lease
terms with the prospective landlord. Any brokerage and advisory fees, tenant fit-
up, moving and other related transaction expenses will be included in the rental
cost estimate for each lease presented to Facilities Council for approval and will
be charged back to the authorized fund source.
11
The UM Office of Legal Affairs (OLA), will document the transaction terms in
the lease, obtain the landlord's and the President's signatures prior to execution
by the Vice President of Administrative Affairs, or its designee. Certain leases
will also require the Office of the Attorney General and Board of Regents (BOR)
review and approval prior to execution by the President and/or the University
System of Maryland Chancellor. OLA will obtain the necessary approvals.
Upon full execution of the lease, OLA will retain the original and the Office of
the Vice President for Administrative Affairs will update the UM Rent Roll.
The unit as tenant will receive monthly invoices for rent and other charges under
the lease and shall ensure that they are paid in a timely manner.
e. Campus Projects
Campus projects are facility improvements or new construction projects
that cost under $1 million which may be approved by the UM
administration's Facilities Council.
Examples range from modifications to subdivide a space to renovating an entire
office suite to support new/changed programs or equipment.
The FM services related to a campus project may include:
12
- a written detailed scope of work;
- a graphic layout/plan of the construction work;
- a conceptual budget will be provided if the user needs preliminary
information for a decision to proceed (no fee charged, budget will be
provided as a range);
- a detailed budget for the total project costs including design (if applicable),
fees, contingency, design review, new construction/renovation, project
management, construction inspection, life safety review,
data/telecommunications, furniture/equipment, special cleaning and moving
as appropriate. The cost for a detailed budget done by in-house staff is $500;
work associated with the detailed budget includes a line item estimate of
costs for the scope of work, a space plan/layout for the area to be modified
and a project schedule. Some detailed budgets may require specialized
expertise of outside consultants at a cost of $500 plus the cost of the outside
consultant. If the project is implemented, the $500 charge is applied to the
total cost of the project.
- a proposed general schedule (duration in number of days/weeks/months) for
the project;
- interaction with the O&M unit that will execute the work;
- authorization of funding (requires a detailed budget if campus funds are
requested);
- design; A 4.5 percent fee will be applied to projects designed with outside
firms. The cost of the design is in addition to the fee. A 10.5 percent fee will
13
be applied to projects designed by FM staff; and
- construction.
For campus projects costing more than $100,000 that the customer requests
partial funding, colleges/departments/divisions forward project requests through
their Dean/Vice President to FAC (March). A detailed budget prepared by FP is
required for all projects to be considered by FAC. The customer must get the
Vice President's endorsement that the project is one that requires further
investigation by FP and has a good chance of being implemented.
Campus projects funded by the customer or costing $100,000 or less are routed on
a RFMS form directly to FP. For fullest consideration, these requests must be
submitted by January to be evaluated for construction implementation during the
summer time period and October to be evaluated for construction implementation
during the winter break.
A Project Manager in FP will be responsible for the project from idea generation
(preparation of scope of work, budget and implementation schedule) through
completion of design. The FP Project Manager will:
- meet with the customer to develop scope of work, budget and schedule. (If
the customer is providing funds for the project and wants to bypass the need
for a project budget, the customer must guarantee to cover the cost of all
services. An outside architect/engineer is required to complete the functions
14
that a Project Manager would perform. Project approval by FP is required
prior to implementation.
- obtain TFC input and approval for all projects involving teaching facilities
and facilities actions that may affect teaching facilities.
- provide direction on the method for implementing construction and the
project schedule.
- obtain the customer's and appropriate VP's agreement/signature on scope of
work, budget and schedule.
- prepare the agenda item for the necessary approval authorities (e.g., FC, FIS,
ADSB).
- notify the customer, service providers (Office of Information Technology,
Department of Business Services, Building Services, etc.) and O&M of the
action of the approval authority.
- implement appropriate architect/engineer selection process, if outside design
services are required
- conduct a design initiation meeting with the customers and other university
representatives as required.
- review requests and make a recommendation on scope additions/changes or
quality upgrades.
A plant fund account will be established by the Comptroller's Office following
project approval and funding authorization. Multi-year funding authorizations
can be accommodated in plant fund accounts. All funds for project expenses
managed by FM will be transferred to the plant fund account to which all project
15
expenses will be charged. Upon financial close-out of the project, unspent funds
will be returned proportionately to the contributing units/sources.
Design Procedures
- The architectural firm/in-house design staff meets with customers and other
university representatives (O&M and B&LS staff, TFC representative,
Department of Environmental Safety Staff, etc.) to gather information and
prepare a schematic design.
- The customer and others review and comment on the schematic design.
- The architectural firm/in-house design staff incorporates all appropriate
review comments directed by UM and the schematic design is approved by
FP and the customer.
- The customer and others review and comment on all subsequent design
submissions which are dependent on the complexity of the project (design
development, 50 percent construction documents, 95 percent construction
documents and 100 percent construction documents).
- Each subsequent design submission is approved by FP and the customer.
- FP Project Manager provides written comment for conformance to project
scope at each design submission.
- If the customer requests a scope change during design, the request must be
reviewed by FP. A scope change is defined as an adjustment (additional
work or quality upgrade) that will result in an increase to the project budget
or the project square footage or changes to the approved room uses. Changes
16
requiring additional funding are funded either by the customer or require the
customer to submit a supplemental funding request to be forwarded by FP to
the approving authority. The FP Project Manager will make a
recommendation to the approving authority and the customer of the action.
The construction phase of campus projects will be executed by O&M. The O&M
Project Manager will be responsible for the project from the bidding phase
through construction completion and financial close-out.
Construction Procedures
- Upon completion of design, the O&M Project Manager requests proposals
from one of the construction vendors, requests the procurement office to bid
the project or assigns the project to be executed by the In-house Construction
unit.
- A contract for construction is awarded.
- O&M Project Manager works with the customers to establish the substantial
completion date.
- If the customer requests a scope change during construction, the request must
be reviewed by FP. The FP Project Manager will make a recommendation to
the approving authority and the customer of the action.
- As the project progresses through construction, the contingency accounts are
used to cover the cost of items not foreseen in the project scope at the time of
approval. These items include latent conditions and design adjustments. The
17
construction contingency accounts are not to be used to fund scope changes.
Scope changes, if desired by the customer, are funded by the customer or by
allocation of supplemental funding by the approving authority.
- O&M Project Manager coordinates with the FM Move Coordinator and with
the customer to ensure delivery and installation of furniture and other
moveable equipment, voice and data services, moving services and keys are
provided. The O&M Project Manager will coordinate the project schedule
with other service providers (Office of Information Technology, Department
of Business Services, Building Services, etc.) by making contact by phone or
e-mail at the appropriate time for coordinated services. The customer must
identify a departmental move coordinator to act as the on site contact for
equipment, furniture, voice and data, signs, moving and keys for the project.
The departmental move coordinator or other staff in the department will
complete all necessary forms for voice and data, keys, moving, etc.
- Prior to occupancy, O&M Project Manager completes a site walk through of
the project with the customer and FP. The O&M Project Manager generates
a punch list of items, identifies warranty problems and develops a schedule to
complete the project. O&M works with the customer to correct warranty
problems.
- O&M Project Manager obtains signature of customer and O&M AD for
Maintenance on letter of substantial completion acknowledging and
accepting that all work has been done.
- Upon construction completion, the O&M Project Manager's goal is to
financially close-out the project within 60 days.
18
f. Capital Projects
Capital Projects are those improvements for new facilities or major
renovations that cost $1M or more and require approval beyond the UM
administration's Facilities Council (i.e., University System of Maryland
Board of Regents and/or the Maryland State Legislature).
Budgeting
- Colleges/departments/divisions forward project requests through their
Dean/Vice President to FAC (September). A detailed budget prepared by FP
is required for all projects to be considered by FAC.
- A 3.75 percent fee will be applied to all capital project expenditures,
regardless of fund source starting in FY 2001.
- FAC reviews all project requests and prepares a recommended 10-year
Capital Improvement Program (CIP) (includes Capital Facilities Renewal
funded projects over $1M) and a recommended 10-year System Funded
Construction Program (SFCP) (January).
- Facilities Council reviews and approves the 10-year CIP and 10-year SFCP
(February/March).
- FP prepares the required documentation for the 10-year CIP and 10-year
SFCP for submission to USMH (March).
- The University of Maryland Board of Regents recommends a five-year CIP
and SFCP and provides funding authorization for the first year of the SFCP
(June).
19
- Funds for projects in the first year of the five-year SFCP are available (July).
- The five-year CIP is submitted to the State Department of Budget and
Management (DBM) (July).
- DBM recommends a five-year CIP to the Governor (November).
- The Governor's recommended five-year CIP is published (late January).
- The Maryland State Legislature approves funding for projects in the first year
of the five-year CIP (April).
- Funds for projects in the first year of the five-year CIP are available (July).
- A plant fund account will be established by the Comptroller's Office
following project approval and funding authorization. All funds will be
transferred to the plant fund account to which all project expenses will be
charged.
CIP Projects
- Following UM approval of the CIP request, FP initiates development of the
Part I program to meet external deadline requirements.
- FP works with the customer to prepare a Part I program that justifies and
describes the project including a room by room space list, special space
requirements, site analysis and assessment of capital equipment that will be
needed to support the project.
- FP obtains TFC input and approval for all projects involving teaching
facilities and facilities actions that may affect teaching facilities.
- Facilities Council approves the Part I program executive summary which
20
includes the scope/overview, justification, space and population summaries,
site and financial plans as appropriate.
- The Part I program is submitted to the USMH for submission to the state
review agencies (DBM, and the Maryland Higher Education Commission -
MHEC).
- The state review agencies prepare program comments and questions.
- FP prepares responses with input from the customers and others as needed.
- The state review agencies (DBM and MHEC) approve the Part I program.
- FP initiates development of the Part II program to meet external deadline
requirements.
- FP works with the customer and others to prepare the Part II program that includes a
detailed description of the scope of work (including a space requirement sheet for
each room) and the scope of architectural/engineering services required. Any
program changes must be approved by the Facilities Council, USMH, and the state
review agencies.
- The Part II program is submitted to the USMH for submission to the state review
agencies.
- The state review agencies prepare program comments and questions.
- FP prepares responses with input from the customers and others as needed.
- The state review agencies approve the Part II program.
21
SFCP Projects
- Following UM approval of the SFCP request, FP initiates development of the Part I
program.
- FP works with the customers to prepare a Part I program that justifies and describes
the project (including a room by room space list).
- FP obtains TFC input and approval for all projects involving teaching facilities and
facilities actions that may affect teaching facilities.
- Facilities Council approves the Part I program executive summary which includes the
scope/overview, justification, space and population summaries, site and financing
plan, and approves proceeding with a Part II.
- FP works with the customers, AEC Project Manager, O&M Staff and others
to prepare a Part II program.
- Any program changes must be approved by the Facilities Council and
USMH.
Project Implementation
- Upon program and funding approval, AEC prepares an implementation plan
designating the financial arrangements, schedule and construction
methodology that the President submits to USMH.
Selection of Architectural Firm
- AEC prepares an A/E selection Request for Proposal (RFP).
- Upon program and funding approval, AEC submits the RFP to DPS to
advertise for an architectural firm to design the project.
22
- Upon receipt of technical proposals, AEC chairs a committee to review
proposals. AEC is the lead university representative, and requests
participation from the customers and others. Through several steps, the
committee rank orders the firms.
- AEC negotiates the fee with the top ranked firm. AEC requests input from
the customers and others as needed.
- If the contract exceeds $500,000, approval is required from the Board of
Public Works (BPW).
- After appropriate approvals, AEC requests DPS to issue the design contract.
Upon issuance, AEC administers the design contract.
Design
- Upon approval of the design contract, AEC conducts a design initiation
meeting that will include FP, the customers and other university
representatives.
- The architectural firm meets with customers and other university
representatives to gather information and prepare a schematic design.
- The customer and others review and comment on the schematic design. AEC
presents the schematic design to the Architectural Design Standards Board
(ADSB) for review. ADSB provides a recommendation on the schematic
design and design development submissions, and AEC presents the
recommendations to Facilities Council for approval. AEC presents the
schematic design submission to the State Architectural Review Board (ARB)
23
if required, for review and comment.
- The architectural firm incorporates all appropriate review comments of the
design team directed by UM and the schematic design is approved by AEC
and the customer.
- The customer and others review and comment on all subsequent design
submissions (design development, 50 percent construction documents, 95
percent construction documents and 100 percent construction documents).
- Each subsequent design submission is approved by AEC and the customer.
- FP provides written comment for conformance to project scope at the final
design submission.
- If the customer requests a scope change during design, the request must be
approved by the Facilities Council. For CIP projects, program changes must
be approved by the Facilities Council, USMH, and the state review agencies.
For SFCP projects, program changes must be approved by the Facilities
Council and USMH.
- Scope deletions that do not compromise standards/specifications must be
approved by the Vice President for Administrative Affairs and university
administration.
Construction
- Upon design completion and construction funding approval, AEC requests
the DPS to bid the project.
- The project is awarded after BPW approval of the contract price.
24
- If the customer requests a scope change during construction, the request must
be approved by the Facilities Council. For CIP projects, program changes
must be approved by the Facilities Council, USMH, and the state review
agencies. For SFCP projects, program changes must be approved by the
Facilities Council and USMH.
- As the project progresses through design and construction, the contingency
accounts are used to cover the cost of items not foreseen in the project scope
at the time of approval. The contingency accounts are not to be used to fund
scope additions/changes or quality upgrades. These situations, if desired by
the customer, are funded by the customer or by allocation of supplemental
funding by the approving authority.
- AEC works with the customer to establish the substantial completion date
and develop a punch list. AEC coordinates with the customer to ensure
delivery and installation of furniture and other moveable equipment, voice
and data services, moving services and keys are provided. The customer
must identify a move coordinator to act as the on site contact for equipment,
voice and date, moving and keys for the project. The departmental move
coordinator or other staff in the department will complete all necessary forms
for voice and data, keys, moving, etc.
- After occupancy, AEC completes a site walk through of the project with the
customer, FP and O&M to generate a punch list of items, identify warranty
problems and develop a schedule to complete the project. AEC/O&M works
with the customer to correct warranty problems. (Warranty periods extend
25
two years after substantial completion.)
Furnishings and Equipment
CIP Projects
- The state requires submission of a detailed capital and operating equipment
list when the university is requesting construction funding. AEC initiates
development of this list in time to meet this deadline. This comprehensive
list contains every item of moveable equipment needed, along with its
estimated price. It includes both capital equipment with a greater than 15-
year life expectancy such as desks, chairs, tables, file cabinets, etc. and
operating equipment with a less than 15-year life expectancy such as
computers, copy machines, fax machines, A/V equipment, etc.
- AEC coordinates the submission of the list and requests input and
information from the customers and others.
- The list is submitted to the state review agencies via USMH.
- AEC responds to state agency questions with input from the customers.
- The state approves the equipment list and the budget amounts.
- Upon funding authorization, AEC initiates requisitions for capital equipment.
- Customers and others prepare operating equipment specifications for
requisitions, with AEC coordinating.
- DPS purchases the equipment.
- AEC coordinates with the customer, contractors and vendors to receive and
26
oversee equipment installation.
- AEC certifies receipt of equipment prior to any payment.
SFCP Projects
- The State does not require equipment lists for SFCP projects. However,
AEC and the customer may determine that a list is needed in order to
prioritize equipment purchases within the project budget and to provide
information to the A/E during design. AEC coordinates the development of
the list with input from the customers.
- Upon funding authorization, AEC initiates requisitions for equipment.
- Customers and others prepare equipment specifications for requisitions, with
AEC coordinating.
- DPS purchases the equipment.
- AEC coordinates with the customer, contractors and vendors to receive and
oversee equipment installation.
- AEC certifies receipt of payment prior to any payment.
27